The back tee was a paltry 1200 sq. feet and after reshaping is now 2700 sq feet!! This new tee will give us many more tee placements to distribute the wear.
|  | 
| The back tee- half the width of the forward tee. 20+ft. of rough wasting space. | 
|  | 
| The machines arrive and digging begins. The mini-ex carves a soft taper off the back of 12 Tee. | 
|  | 
| Load after load hauled away and stock piled at our shop for future projects. | 
|  | 
| The floor almost completed to a 8" depth. This was then laser leveled for a small amount taper for drainage. | 
|  | 
| After drain lines were dug and pipes installed, approx. 80 tons of tee mix was added and leveled. | 
|  | 
| The surface was plate tamped(compacted) then spun with our bunker machine. Sod Arrives! | 
|  | 
| Penn -trio sod installed on the tee along with turf type tall fescue rough sod for the border. | 
|  | 
| FINISHED PRODUCT! | 
 
Looks great!